Remodel Timelines: Kitchens, Baths, Additions & More

Permit and Construction Timelines for San Diego Remodels

Project Timelines: Kitchens, Baths, Additions & Whole Home Remodels


October 17, 2025

If you’re planning a remodel, the question I’m asked most is, “How long will this take?” With 20 years of experience managing hundreds of projects across San Diego, I can provide you with a clear and realistic roadmap. Below, I’ll walk you through timelines for our two delivery models—our Expedited Kitchen & Bath process and our Design-Build model for larger scopes—plus what speeds things up (and what slows them down). I’ll start with a quick snapshot, then break down each phase so you know exactly what to expect.

For San Diego homeowners who are ready or seriously considering a remodel, this guide is for you. I’ll show you what a realistic schedule looks like in our city and county, how permitting typically works here, where small-jurisdiction delays can occur, and how cabinet/material lead times influence start dates. If you want fewer surprises and better decisions, keep reading—next, we’ll look at quick wins in our expedited kitchen & bath track and when it makes sense to choose full design-build.

🎧 Prefer to listen? Hit play—I’ll walk you through San Diego permits, lead times, and real start dates.


Key Takeaways

  • Permits run in parallel with planning; San Diego City/County no-plan permits are often <1 week, while smaller jurisdictions (Poway, Chula Vista, Santee, etc.) can add months.
  • In our Expedited Kitchen & Bath, you can expect to see your concept and proposal within 1–2 weeks, followed by VEC and selections within the next two weeks. Bathrooms are built in ~4–8 weeks; kitchens in ~6–10 weeks.
  • Cabinet lead times (typically 6–8 weeks) often set the kitchen start date; we won’t begin demo until delivery windows are confirmed and locked.
  • In Design-Build, plan on ~6 weeks to conceptual design after retainer, then ~12 weeks of pre-construction after contract (A/E, selections, permits, ordering, subs, shop drawings) before construction begins.
  • Living in the home and phased work extend timelines; scope and structural complexity also do.
  • We protect your schedule with clear start triggers: permits approved, materials ordered, delivery windows confirmed—then we start.

▶️ Prefer to watch? This 6-minute video walks you through San Diego permits, lead times, and realistic timelines.

Want the quick version by project type? Jump to the TL;DR below.


TL;DR: Timelines at a Glance

Project / Model Design & Planning Permits* Pre-Start Triggers Typical Build Duration
Bathroom (Expedited K&B) Concept & proposal: 1–2 wks; VEC next wk; selections the following wk SD City/County: no-plan <1 wk; some smaller jurisdictions can be months Selections ordered, delivery windows set, permits in hand 4–8 weeks
Kitchen (Expedited K&B) Same as above Same as above Cabinet lead time drives start (typically 6–8 wks); permits in hand 6–10 weeks
Bathroom (Design-Build) Conceptual design ~6 wks from retainer In pre-con ~12 wks to start after contract (A/E + selections; then permits + orders + subs + shop drawings) ~12 weeks
Kitchen (Design-Build) ~6 wks In pre-con ~12 wks to start ~16 weeks
Whole Home (Design-Build) ~6 wks In pre-con ~12 wks to start ~20 weeks (more if complex)
Additions (Design-Build) ~6 wks In pre-con ~12 wks to start ~5 months (12+ months if large/complex)

*Durations are typical ranges based on San Diego conditions and not guarantees. Permits typically run concurrently with planning. Smaller jurisdictions—such as Poway, Chula Vista, and Santee—can add months.

Process at a Glance

1
Concept
Design & proposal
2
VEC / Selections
Verify site + choose products
3
Permits / Ordering
Jurisdiction + lead times
4
Start Triggers
Permits • materials
delivery • trades
5
Build
Construction phase

Next, I’ll outline how our Expedited Kitchen & Bath model operates, from consultation to completion of the punch list.


Model 1: Expedited Kitchen & Bath (Single-Room, Streamlined)

I designed this model for homeowners who want a swift, well-managed kitchen or bath without reinventing the wheel.

Phase 1 — Concept & Proposal (Weeks 1–2)

After your in-home consultation, we’ll invite you back to our showroom in 1–2 weeks to review your conceptual design and proposal. You’ll see layout direction, key finishes, and an itemized scope so you can say yes with confidence.

Up next: what happens the moment you sign—VEC and selections.

Phase 2 — VEC & Selections (Weeks 2–4)

Once you sign, we schedule your VEC (Verification & Engineering Coordination) meeting, usually for the following week. We confirm dimensions, utilities, and any structural nuances. The following week, we will host your product selections and cabinet meeting to finalize orders and confirm delivery dates. For bathrooms, we typically start ~4–6 weeks after contract (assuming City/County permitting and no unusual lead times).

Next, let’s talk permits—and why San Diego City/County is usually fast, while some smaller cities aren’t.

Permitting (Runs During Planning)

  • San Diego City/County: Most kitchens and baths qualify for no-plan permits, typically under one week.
  • Smaller jurisdictions (e.g., Poway, Chula Vista, Santee, etc.): Can take several months.
    We process permits while we’re selecting and ordering materials, so in most cases, permits don’t add time—unless we’re in a slower jurisdiction.

San Diego Permit Snapshot: The City and County of San Diego often allow no-plan permits for many kitchens/baths (< 1 week). Smaller cities (Poway, Chula Vista, Santee) may require a complete plan review (can be months).

📄 Pro Tip: Smaller Cities Often Need Full Plan Review
  • Ask early: confirm whether your jurisdiction uses no-plan permits or requires plan review.
  • Pad the calendar: add a buffer of several weeks to months for Poway/Chula Vista/Santee.
  • Submit complete sets: clean drawings + specs reduce back-and-forth and resubmittals.

Now, the most significant start-date driver for kitchens: cabinets.

Cabinet Lead Times (Kitchens)

Cabinets often determine your construction start. The typical lead time is 6–8 weeks, but it varies by line and manufacturer. Because we partner with multiple cabinet lines, we can switch to a faster option when timing is critical.

Need a realistic kitchen start date?

We’ll check cabinet lead times and your jurisdiction, then give you an accurate window.

Book Your Consultation

🗓️ Pro Tip: Lock Cabinets = Lock Your Start Date
  • Decide fast: choosing the line/finish in week 2–3 keeps a 6–8 week clock honest.
  • Have a Plan B: we carry multiple lines—swap to a faster option if timing matters.
  • Confirm delivery: don’t demo until the delivery window is in writing.

With permits and materials aligned, here’s how long construction actually takes.

Construction Durations

  • Bathroom: 4–8 weeks
  • Kitchen: 6–10 weeks
  • Multiple spaces/whole home within the K&B model: up to 16+ weeks, especially if phased or if you’re living in the house (access and sequencing add time).
  • Single-room K&B projects are typically less invasive, which helps keep durations tight.
📈 Pro Tip: Freeze Scope Before Demo
  • Batch changes now, not later: mid-build tweaks ripple into subs, inspections, and lead times.
  • Price alternates up front: keep 1–2 material alternates quoted to avoid delays.

Expedited Kitchen & Bath — Recent Highlights

Encinitas kitchen remodel with large sink-wall window and bright natural light Poway kitchen remodel featuring quartz island and two-tone cabinets Carmel Valley spa bathroom with double vanity and soaking tub

For larger projects, additions, or whole home transformations, our Design-Build model is the better fit—here’s how that timeline works.


Model 2: Design-Build (Major Remodels, Additions, Whole Homes)

When you’re reconfiguring space, adding square footage, or undertaking a comprehensive whole home update, our Design-Build process aligns architecture, engineering, selections, permitting, and construction under one accountable team.

Phase 1 — Conceptual Design (~6 Weeks from Retainer)

Once your retainer is signed, we will proceed with the conceptual design and bring you back to the showroom in approximately six weeks for your design + proposal presentation. Complexity, optioning, and decision speed can stretch or compress this window.

⚡ Pro Tip: Faster Decisions = Faster Start
  • Set a 48–72 hr rule: target approvals on drawings and selections within 2–3 days.
  • One point of contact: pick a household “decider” to avoid re-work.
  • Group selections: schedule one focused showroom visit vs. many small trips.

After you approve the construction contract, we enter the pre-construction phase—the engine of an on-time start.

Phase 2 — Pre-Construction (~12 Weeks to Start After Contract)

Pre-construction is the engine room of an on-time remodel. That is where we lock drawings, engineering, permits, materials, and trade schedules, ensuring your start date is realistic—not optimistic. In San Diego, coordinating inspections, lead times, and HOA/condo constraints up front saves weeks later. We won’t swing a hammer until the pieces are sequenced and ready, which is how we protect your schedule and your home.

  • Weeks 1–6: Architecture, engineering, and selections.
  • Weeks 7–12: Permitting, material ordering, subcontractor scheduling, and shop drawings.
    San Diego City/County permits typically average around 6 weeks, while permits in smaller jurisdictions can take longer. We start only after permits are approved, long-lead materials are ordered with confirmed delivery windows, and trades are scheduled—so your start date is real, not hopeful.
✅ Pro Tip: Start Triggers = On-Schedule Build
  • Permits approved ✔
  • Long-lead materials ordered with delivery windows ✔
  • Shop drawings approved ✔
  • Subs scheduled and sequenced ✔

If one box isn’t checked, hold the start—downtime is costlier than patience.

With the pre-construction set, let’s talk about how long the actual build takes by project type.

Construction Durations (Typical)

These ranges reflect typical San Diego conditions, the cadence of inspectors, and the realities of working in occupied homes. Your scope, structural needs, and whether you’re living in the house all influence the final timeline. Think of these as reliable targets with buffers baked in from years of delivering here locally.

  • Bathroom: ~12 weeks
  • Kitchen: ~16 weeks
  • Whole Home: ~20 weeks
  • Additions: ~5 months
  • Large/Complex (e.g., ~5,000 sq. ft., major structural, high-end finishes, exterior scope): ~12+ months
    For context, a ~2,500-sq-ft whole home project with limited structural work can often be delivered in approximately 5 months of construction.
📏 Pro Tip: Match Finish Level to Schedule
  • High-end finishes (stone fabrication, custom metal, built-ins) lengthen durations.
  • Phase exterior work (roofing, stucco/paint) around weather windows to avoid slips.

Design-Build — Whole Home & Major Remodels

Pacific Beach whole home remodel with open kitchen and island seating San Diego kitchen remodeling project with contemporary finishes Modern open-concept kitchen after full renovation

Timelines are shaped by more than scope and permits. Next, I’ll show you the factors that can speed things up—or slow them down—and how to plan around them.


What Speeds Up—or Slows Down—Your Project

Every project has two sets of levers: the external (jurisdictions, inspections, supply chains) and the internal (decisions, scope, access). Knowing which is which helps us prioritize smartly and avoid avoidable slowdowns. We’ll highlight the key drivers so you can see where time is saved or lost.

  • Jurisdiction & permit path: No-plan permits are fast; full plan reviews in smaller cities can add months.
  • Cabinet/material lead times: Kitchens, in particular, hinge on cabinet delivery.
  • Decision speed: Approving layouts, finishes, and shop drawings quickly keeps momentum.
  • Scope & sequencing: Single room vs. multiple spaces; phasing adds time.
  • Living in the home: It’s doable, but it typically extends timelines due to access and staging.
  • Structural & engineering complexity: More review, more coordination.
  • Change orders during construction: Mid-stream changes ripple across trades and inspections.
🏠 Pro Tip: Living At Home? Plan for Phasing
  • Create zones: dust barriers + a temporary kitchen/bath keep life moving.
  • Access windows: consistent daily access helps crews finish faster.
  • Expect add-time: phasing typically extends duration—build in margin.

So how do we keep all of this on track? Here are the safeguards we’ve refined over two decades in San Diego.


How We Protect Your Schedule (and Sanity)

This is our playbook: clear start triggers, parallel permitting, disciplined shop drawings, and early trade alignment—refined over two decades in San Diego. It’s how we pass inspections the first time and keep subs marching in sequence.

  • Clear start triggers: We don’t start until permits are approved, materials are ordered, and delivery windows are confirmed.
  • Multiple cabinet lines: We can pivot when lead times threaten your start.
  • Concurrent permitting: We run permits during planning—never after.
  • Detailed shop drawings & early trade alignment: We solve problems on paper, not in your living room.
  • Proactive communication: You’ll know what’s happening, who’s on site, and what’s next—always.

Want to do your part to keep things moving? Here’s how homeowners can help accelerate timelines.


Client Prep Tips to Keep Things Moving

Homeowner participation is a quiet superpower. Quick approvals, readiness for site access, and flexibility on alternates can compress weeks. These simple moves keep materials flowing and crews productive, which directly shortens your timeline.

  • Make selections promptly and approve drawings quickly.
  • Consider temporary relocation during invasive phases to avoid phasing delays.
  • Finalize scope before demo to minimize change-order domino effects.
  • Be open to alternatives (e.g., a different cabinet line) if a lead time jeopardizes your target start.
🎯 Pro Tip: Front-Load the Long Leads
  • Decide on cabinets, windows, appliances, and specialty tile first.
  • Keep a tier-2 alternate ready for any item with unstable lead times.

Still weighing Expedited Kitchen & Bath vs. Design-Build? Let me help you choose the right path.


Which Model Fits Your Project?

  • Choose Expedited Kitchen & Bath if you’re focused on one room (or a couple) and want a streamlined path with proven selections and faster starts.
  • Choose Design-Build if you’re reconfiguring space, adding on, or tackling a whole home—you’ll benefit from integrated architecture, engineering, and construction under one roof.

Before we wrap up, here are quick answers to questions I get every week.


Frequently Asked Questions by San Diego Homeowners

Do permits add time?

Usually, no—we process permits during the planning stage. Smaller jurisdictions can add months, and we’ll factor that in up front.

Why do kitchens start later than baths in the Expedited model?

Because of cabinets. We won’t demo until we’ve locked the cabinet delivery window to avoid living without a kitchen longer than necessary.

Can we live at home during the remodel?

Yes, but expect longer durations. Phasing around your family and access windows adds time. We’ll propose a plan that strikes a balance between comfort and speed.

Can you expedite the process if we’re under a tight deadline?

Often, yes—by choosing faster cabinet lines, front-loading selections, and pre-booking subs. Quality and inspections still govern pace, and we won’t compromise them.

How do inspections affect the schedule?

Inspections are required at key milestones (framing, rough MEPs, waterproofing, finals). In San Diego City/County, we can often book within a few days, depending on the jurisdiction; smaller jurisdictions may take longer to process. We “pre-inspect” work with our trade leads to pass on the first visit. If a re-inspection is needed, expect 2–5 extra days depending on the jurisdiction and calendar.

🛠️ Pro Tip: Pre-Inspect With Your Team
  • Checklist walk: have leads review nailing patterns, blocking, fire-caulk, and plate seals.
  • Photo log: snap rough-in conditions—helps if an inspector requests clarification.

Do HOAs or condo boards change the timeline?

Yes. HOA/ARC approvals can add several weeks to the permit process, and many condos have strict work hours, elevator reservations, and noise rules that require phased sequencing. We build those constraints into your schedule up front so your start date and completion target remain realistic.

🏢 Pro Tip: Reserve Elevators & Work Windows Early
  • Submit to ARC early: approvals can add 2–6 weeks—start paperwork in parallel.
  • Book elevator slots: align material deliveries with HOA-approved hours to avoid idle crews.

Why Kaminskiy for Your Timeline-Driven Remodel

We’ve been remodeling San Diego homes since 2005, and our playbook is built on that field experience: realistic planning, disciplined pre-construction, and craftsmanship that finishes on schedule. Whether you need a quick, well-managed bath refresh or a comprehensive whole home transformation, our team follows a tight, transparent process that respects your time and your home.

Ready to plan your timeline?
Let’s review your scope, jurisdiction, and lead times to provide you with a start date you can trust.

Book Your ConsultationSee Our ProcessView Recent Projects


Posted In - Bathroom Remodel, Home Additions, Home Remodel, Kitchen Remodel on Oct 17, 2025